Hudson Valley Sudbury School
  Home  
  Articles  
  Events  
  Store  
  Sudbury Schools  
  Gallery  
  Calendar  
  Contact Us  

Construction and Building Pictures

Building from the Parking Lot
PreviousNext
March 14, 2023
The building from the parking lot location. The cement board will be stucco'ed an off-white color.
Picture Thumbnails
Start of Clearing the Site
Start of Clearing the Site
School Building Site
School Building Site
View of the Entrance
View of the Entrance
Starting to dig the Foundation
Starting to dig the Foundation
More Foundation
More Foundation
Preparing to Blast
Preparing to Blast
After the Blasting
After the Blasting
The Foundation after Blasting
The Foundation after Blasting
Starting the Foundation
Starting the Foundation
Starting the Foundation - 2
Starting the Foundation - 2
Starting the Foundation - 3
Starting the Foundation - 3
Building Footers
Building Footers
Lily and Lisa in the Foundation
Lily and Lisa in the Foundation
Inside the Basement
Inside the Basement
Starting to Pour the Foundation
Starting to Pour the Foundation
Two Trucks at Once
Two Trucks at Once
The Slump Test
The Slump Test
Slump Test Results
Slump Test Results

Walls Finished, on to the Floor
Floor Just Poured
Floor Just Poured
Lowering the Smoother
Lowering the Smoother
Handprints
Handprints
Waterproofing the Basement
Waterproofing the Basement
Support Beams
Support Beams

Floor Panels
The Floor is Partially Done
The Floor is Partially Done
Floor is Done
Floor is Done
Half the Frame is Done
Half the Frame is Done
The Back of the Building
The Back of the Building
The Front of the Building
The Front of the Building
The Trusses Ready Install
The Trusses Ready Install
Placing one of the Trusses
Placing one of the Trusses
More Trusses
More Trusses
Back of Building - Trusses Up
Back of Building - Trusses Up
Start of the Roof
Start of the Roof
Dormer Closeup
Dormer Closeup
The Completed Roof in Snow
The Completed Roof in Snow
The Front of the Building
The Front of the Building
The Back of the Building
The Back of the Building
The Exterior Trim Completed
The Exterior Trim Completed

The Building is Wrapped
Insulating the Walls
Insulating the Walls
Insulation
Insulation

The Main Hallway
Front of the Building with Trim
Front of the Building with Trim
Kitchen Insulation
Kitchen Insulation
Kitchen Sheetrock
Kitchen Sheetrock
Kitchen Insulation - Other Angle
Kitchen Insulation - Other Angle
Kitchen Sheetrock - Other Angle
Kitchen Sheetrock - Other Angle
Kitchen Tile Being Installed
Kitchen Tile Being Installed
Kitchen Floor Mostly Done
Kitchen Floor Mostly Done
Kitchen Floor Complete
Kitchen Floor Complete
Bathroom Hall
Bathroom Hall
Bathroom Tiles
Bathroom Tiles

No More Porta Potty!
Den Entry
Den Entry
Lounge Entrance
Lounge Entrance
Lounge Floor
Lounge Floor
Art Room
Art Room
Building from the Parking Lot
Building from the Parking Lot

Center of the Parking Circle
Building from the Entrance
Building from the Entrance
Terrace and Tree Holes
Terrace and Tree Holes
The Hall
The Hall
The Window Trim
The Window Trim
Kitchen Trim
Kitchen Trim
Door Frames
Door Frames
4 Levels of Moulding
4 Levels of Moulding
Hallway/Lounge Before Paint
Hallway/Lounge Before Paint
Hallway/Lounge Painted
Hallway/Lounge Painted

Painting - Hallway to Kitchen

Stucco Buckets
Stucco Being Applied
Stucco Being Applied
Interior Door Stain
Interior Door Stain
Lounge to the Patio
Lounge to the Patio

Patio Trees

Wall Sconce
Our own Road Sign
Our own Road Sign
Paving Beast
Paving Beast
Driveway Looking  Up
Driveway Looking Up
Driveway Looking Down
Driveway Looking Down
Handicap Ramp and Porch
Handicap Ramp and Porch
Building and Driveway
Building and Driveway
Copyright © 2004 Hudson Valley Sudbury School